Health facilities for Dwarkaites postponed again...



Complete Status Report : C/o 750 Beds Hospital at Sec-9, Dwarka, New Delhi.

Zone/Circle/Div : Building Project Zone B 2 / B 23 / B 24 / B 232

Salient Features :
Plan Approval Position : 

Department Date of Submission Date of Approval
DDA 18.08.2008 --
CFO 06.04.2009 09.10.2009
DUAC 06.04.2009 07.12.2009
EIA 26.08.2009 30.04.2010
DMRC 26.11.2008 --
AAI 25.04.2009 --

Cost: Rs. 35000.00 Lacs. (AA&ES) Dated. 30.11.2007

Progress Details :
Date of Start : Date of Completion :
Expected Date of Completion :
Contractors :
Expenditure :
Civil : Rs. 87.47 Lacs (Oct 2011) % Progress : % (Oct 2011)

Present Position :
Civil As on 09/04/2012:
Revised estimate of Rs. 684.44 crore has been submitted to DHS on 14-11-2011. Work shall be completed in 40 months after sanction. DDA vide their letter No. F.13(273)/2001/Bldg./01 dated 05.01.2012 has sanctioned building plans. The building plans are being reviewed by team of Doctors of MAMC to reduce the plinth area.

Main Bottlenecks : Civil

See original info

MURDER of a Premature Hospital in Dwarka...

Labels: , , , ,